Calculating and Determine Rex Idler Load

Photo: Industrial conveyor belt - geograph.org.uk - 4373595 by Martin Pearman · CC BY-SA 2.0 via Wikimedia Commons

Answer Selection of the Rex Idler Series is based on the following factors: belt width; belt speed; idler troughing angle capacity, idler spacing; weight of belt; material lump size; type of service, and environmental conditions.CARRYING IDLERTo…

Selection of the Rex Idler Series is based on the following factors: belt width; belt speed; idler troughing angle capacity, idler spacing; weight of belt; material lump size; type of service, and environmental conditions.
CARRYING IDLER
To select the correct Carrying Idler Series, it is necessary to determine the Static Load per idler.
1.Determine Static Load Per Idler
LS = Si TPH x 33.3 + Wb
FPM
Where:
LS = Static Load Per Idler in Pounds
Si = Idler Spacing in feet (See table 5 for recommended Idler Spacing)
TPH = Required Conveyor Capacity (Use TPH of material to be conveyed).
FPM = Belt Speed
Wb =Belt weight Pounds per foot. (See table 6 for estimated average belt weights).

2.Determine Working Load Per Idler
Lw = Ls (Fsp) (FL) (Fse) (Fe)
Where:
Lw = Idler Working Load (pounds per idler)
Ls = Static Idler Load (from 1 to above)
Fsp = Speed Factor (Table 7)
FL = Lump Factor (Table 8)
Fse = Service Factor (Table 9)
Fe =Environmental Factor (Table 10)

3.Select Carrying Idler Series
Using the belt width and troughing angle, select the IDLER SERIES from table 11, with a load rating greater than Lw. (NOTE: if Ls is larger than Lw, use Ls).
Determining troughing angle is based on required capacity, economics and preference. Type of belt also has to be considered. in a large percentage of new installations, 35° troughing angle will be satisfactory.

Sourcing desk

Need the machine, not just the theory?

Send the specification and destination port. You get a factory-direct price, lead time and shipping estimate within two business days.