HOW TO SELECT A MINE HOIST

4,016 words About 18 min read Published by YJMT
Overhead crane
Answer Here is a guide to calculate how to size a mine hoist while you know the desired capacity (TPH) and depth for vertical shaft.Find: Skip load, and wire rope sizes, hoist size and motor horsepower.The main problem in selecting a hoist for a…

Here is a guide to calculate how to size a mine hoist while you know the desired capacity (TPH) and depth for vertical shaft.

Find: Skip load, and wire rope sizes, hoist size and motor horsepower.
The main problem in selecting a hoist for a given capacity and depth is deciding on the proper skip load (payload). a larger load hoisted at slower speeds requires less horsepower, but at the expense of increased rope diameter which, in turn, increases the drum diameter, gearing, etc.
In selecting a skip size, therefore, it is helpful to know the relationship between skip load, speed, and capacity for the given depth. such a relationship is shown in Graph A. these curves show that for any capacity, as skip as decreases, the speed increases to the point where the cycle consists of only acceleration and retardation, with no full speed time (approximately 63 f.p.s. at 1600 ft. in Graph A).
These six curves represent the factor of safety laws or standards for drum and friction hoists in the United States, Canada, and a European country.
These curves are shown to point out the wide variations which indicate that rope factors of safety are not easily established, absolute values. the step curve is the M S H a minimum allowable when men are being hoisted. the ANSI (M11.1 – 1980) curves are that standard’s requirement for drum hoisting and Koepe hoisting considering the maximum load only for men or material. some states have laws that are more rigid, and the various regulations change from time to time. the factors of safety shown should be used as a guide only and the laws in each area should be checked. a high factor of safety is no substitute for a good inspection and maintenance program.
The next step is to select the proper skip load. the left side of the shaded area of Graph a indicates the portions of the curves optimum for Koepe Friction Hoists; the right side shows portions optimum for drum hoists. (Experience has shown that the optimum skip load of a Koepe Friction Hoist usually is larger than that of a drum hoist, for the same tonnage and hoisting depth. by increasing the skip load, it is sometimes possible to jump to the next smallest motor size without greatly increasing the cost of the mechanical equipment. with a drum hoist, the cost of the mechanicals increases more rapidly than with a friction hoist – hence the different optimum areas.)2
From the curve you have constructed, select the proper skip load. Multiply this skip load by.75 to find an approximate skip weight (SW (skip weight) =.75 SL).3
(Consult Graph B to determine K1 and K2 factor of safety.)
To find Rope Size: Solve this equation for diameter:
2The cost of the headframe, skips, loading pockets and ropes enters into the economics when selecting skip loads, but these cost changes are relatively small. (Skip sizes can be varied within limits without changing the shaft selection.) we are not attempting to make an economic comparison between drum and Koepe schemes in this manual – to select one over the other involves a complex study which should include the complete hoisting plants.
3If your skip weight factor is known, use it rather than 0.75. to determine proper friction hoist skip weight, see Graph C.
4Derived as follows:
Braking strength of rope (in tons) = (SL + SW + (wt./ft. of rope x depth)) factor of safety
Expressed in terms of rope diameter, using constants K1 and K2, this becomes K1 d2 = (SL + K2 x depth x d2) factor of safety.
To find Drum Diameter: Consult Graph C and determine the proper D/d ratio number for your hoisting depth. Multiply rope diameter (d) by this number to determine drum diameter (D). Graph C also gives suggested friction hoist T1/T2 ratio and tread pressure limits.
To find face width of Drum Hoist: Select and standard rope diameter rope diameter corresponding to d. then solve one of the following equations for face width:
For Single Drum: (balanced hoisting, single layer)
face width (inches) = S x depth + 15S
D
For Double Drum: (single layer)
(S = groove pitch approximately 1.05 d)
face width (inches) = S x depth + 7S
D
(For each additional layer of rope, eliminate the dead turns (15S or 7S) and increase D by 1.7d.)
To find Motor Horsepower: RMS (HP)
Draw a h.p./time cycle diagram similar to Diagram E or Diagram F and label it.
ta = acceleration time (sec.)
tfs = full speed time (sec.)
tr = retardation time (sec.)
For estimating purposes and simplification, combine Ta1 and Ta2 = ta, and tr1 and tr2 = tr. Creep time is not considered in acceleration or retard time.
From your skip load velocity curve, select the full speed velocity corresponding to the skip load.
Knowing the velocity, and assuming 2.5 f.p.s. for a and r rates, find ta and tr.
ta = tr = V / 2.5
RMS HP for Drum Hoist
Find the approximate equivalent effective weight (EEW) on Graph D.
Using the following steps5, determine h.p. values corresponding to various points in h.p./time cycle Diagram E.
5(Explanations of the abbreviations used in the drum hoist horsepower equations which follow:)
R = depth x rope weight per ft.
TSL = total suspended load = EEW + SL + 2SW + 2R
SLB = suspended load at bottom of shaft = (SL + R) – (V x ta x rope wt. Per ft.)
SLT = suspended load at top of shaft = (SL – R) + (V x tr x rope wt. Per ft.)
6.176 = 100 – E E = 0.85
E
7rest = creep time + idle time
A.(peak accelerating h.p.) = HP1 + HP7 + HP4 + 2 HP3
3
B.(full speed h.p. at end of acceleration period) = HP4 + HP7
C.(full speed h.p. at start or retard period) = HP5 + HP7
D.(retardation h.p.) = HP2 + HP7 + HP5 + 2 HP6
3
HP8 (h.p. required to accelerate motor rotor) = 0.6A x 1.2
ta
HP9 (h.p. required to retard motor rotor) = 0.6A x 1.2
Tr
E.(total h.p. required to accelerate hoist and motor) = a + HP8
F.(total h.p. required to retard hoist and motor) = D + HP9
Note – HP2 and HP9 are negative
The shaded area in Graph a on page 19-14 indicates the approximate economical limits for a given condition. Picking a skip load and speed from a similar skip load/velocity curve is certainly sufficient for general planning. the accompanying graph shows, however, that to obtain the optimum load and speed, actual cost curves should be plotted. Nordberg engineers plot similar curves before making any hoisting system recommendations.
The most reliable drive is the d.c. adjustable voltage system whereby static silicon controlled rectifiers furnish d.c. power for the d.c. drive motor. Rexnord recommends this type of system for most mine hoist installations because of superior performance, lower overall cost, good reliability and safety.
The conversion of a.c. power to d.c. via a motor generator set is recommended if the power system at the mine site cannot tolerate the static drive system’s acceleration power factor swing from a low 0.1 to a high of 0.85 lagging when at full speed. the size of the static-powered hoist drive with respect to the total plant or mine load determines the relative importance of the power factor and therefore each application should be evaluated to determine its effect on the power system and on other connected loads. Normally in the domestic United States the power system is able to handle the average 0.7 lagging power factor.
The following table is an approximate operating and cost comparison of motor-generator sets and static drives used in a typical mine hoist system.
M-G SetStatic Drive
Initial cost of system..................100%90%
Installed cost..............................100%80%
Operating cost,
kwh per ton..................100%90%
Power factor.............................0.80.7
leadinglagging
Kw demand effect....................100%92%
Estimated maintenance time....100%70%
Estimated downtime for
major repair...........................100%30%
Operating characteristics.......Not appreciable difference
Technical competence
required................................100%100%
The a.c. induction motor drive coupled with schemes for automation such as a.c. saturable reactor drive, a.c. eddy current brake drive and the Nordberg a.c. hoisting* system which automatically controls hoist brakes are available but are recommended rarely because of cost and efficiency considerations.
The hydraulic drive which has some of the operating characteristics of the d.c. drive system with the added feature of lower initial capital cost is recommended in lower horsepower situations requiring high torque at low RPM.